Document control
record
A person using Aurecon documents or data accepts the risk of:
a) Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard copy version.
b) Using the documents or data for any purpose not agreed to in writing by Aurecon.
Author signature |
|
Certified by |
|
Name |
Jason Man |
Name |
F. C. Tsang |
Title |
Environmental Team Consultant |
Title |
Environmental Team Leader |
1.2 Construction Works Programme
1.4 Construction Works Programme and Construction Works Area
1.5 Summary of Environmental Status
2.3 Monitoring Parameter and Frequency
2.4 Sampling Depths & Replication
2.8 Action and Limit Level for Water Quality Monitoring
3.2 Noise Monitoring Parameter, Frequency and Duration
3.3 Monitoring Equipment, Methodology and QA / QC Procedure
3.4 Maintenance and Calibration
4.2 Habitat Compensation for the Affected Riverine Habitat
9 Environmental Site Inspection and Audit
9.1 Implementation Status of Environmental Mitigation Measures
10 Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
10.2 Summary of Environmental Non-Compliance. 31
10.3 Summary of Environmental Complaint
10.4 Summary of Environmental Summon and Successful Prosecution
11.1 Works and Potential Environmental Issues in the next Reporting Period
12.2 Comments/ Recommendations
Appendices
Appendix 1.1 Construction Programme
Appendix 1.2 Project Organization Chart
Appendix 1.3 Implementation Status of Environmental Mitigation Measure
Appendix 2.1 Calibration Certificates of Impact Water Quality Monitoring Equipment
Appendix 2.2 Event and Action Plan for Water Quality Exceedance
Appendix 2.3 Impact Monitoring Schedule of the Reporting Month
Appendix 2.4 Impact Water Quality Monitoring Data
Appendix 3.1 Calibration Certificates of Impact Noise Monitoring Equipment
Appendix 3.2 Event and Action Plan for Noise Exceedance
Appendix 3.3 Impact Noise Monitoring Data
Appendix 11.1 Impact Monitoring Schedule of Next Reporting Month
Figures
Figure 1.1 General Site Location Plan
Figure 1.2 Location of Work Areas for the Project
Figure 2.1 Impact Water Quality Monitoring Locations
Figure 3.1 Impact Noise Monitoring Locations
Figure 8.1 Area for Archaeological Survey
Figure 8.2 Layout plan showing distance between the works area at Ha Che and the Lan Fong Study Hall
Figure 8.3 Monitoring Locations of Lan Fong Study Hall at Ha Che
Figure 8.4 Monitoring Locations of St. John’s Chapel near Tai Wo
Tables
Table A1 Summary of EM&A activities in the Reporting Period
Table A2 Summary of Exceedances in the Reporting Period
Table A3 Summary of Exceedances of the Last Reporting Period
Table 1.1 Parties Involved in Project Organisation
Table 1.2 Status of Environmental License, Notifications and Permits
Table 1.3 Summary of Status for Key Environmental Aspects under the Approved Updated EM&A Manual
Table 2.1 Summary of Impact Water Quality Monitoring Stations
Table 2.2 Parameters measured in the Impact Water Quality Monitoring
Table 2.3 Water Quality Monitoring Equipment
Table 2.4 Method for Laboratory Analysis for Water Samples
Table 2.5 Action and Limit Levels for Water Quality
Table 2.6 Action and Limit Levels of Water Quality
Table 2.7 Summary of Exceedance Records of Water Quality Monitoring in the Reporting Period
Table 2.8 Summary of Exceedance Records of Water Quality Monitoring in the Last Reporting Period
Table 3.1 Noise Monitoring Stations during Construction Phase
Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration
Table 3.3 Construction Noise Monitoring Equipment
Table 3.4 Action and Limit Levels for Construction Noise Monitoring
Table 3.5 Summary of Construction Noise Monitoring Results
Table 3.6 Influencing Factors at Noise Monitoring Stations
Table 8.1 Mitigation Measures for Impacted Graded Historic Buildings
Table 9.1 Site Inspection Record
A1. This is the 13th Monthly Environmental Monitoring and Audit (EM&A) Report for Drainage Improvement Works Near Four Villages in Yuen Long (the Project). This report was prepared by Aurecon Hong Kong Limited under Contract No. DC/2022/02 Drainage Improvement Works at Yuen Long – Stage 2 (hereinafter called the “Contract”). This report documents the findings of EM&A works during the reporting period from 1 to 28 February 2025.
A2. A summary of construction activities undertaken during the reporting period is presented below:
§ Site Clearance
§ Breaking Ground
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting
§ Sheet pilling & Backfilling and Compaction; and
§ Removal of Sheet piles, Drain Laying works, Reinstatement
Lin Fa Tei
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Sung Shan New Village
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Tai Wo
§ Site Clearance
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
A3. The monthly EM&A programme was undertaken by the ET in accordance with the approved Updated EM&A Manual. A summary of the monitoring and audit activities during the reporting period is presented in Table A1.
Table A1 Summary of EM&A activities in the Reporting Period
EM&A Activities |
Date |
Water Quality Monitoring |
Ha Che, Lin Fa Tei and Sung Shan New Village: 3, 10, 17 and 24 February 2025
Tai Wo 1, 3, 5, 7, 10, 12, 14, 17, 19, 21, 24, 26 and 28 February 2025 |
Noise Monitoring |
Ha Che, Lin Fa Tei, Sung Shan New Village and Tai Wo 1, 4, 10, 21 and 27 February 2025 |
Weekly Environmental Site Inspection |
A4. No exceedance was recorded in the reporting month. Summary of the environmental exceedance for the reporting month is tabulated in Table A2 & A3.
Table A2 Summary of Exceedances for Water Quality and Noise in the Reporting Period
Environmental Monitoring |
Parameter |
No. of non-project related exceedances |
Total No. of non-project related exceedances |
No. of exceedances related to the the project |
Total No. of exceedance related to the project |
||
AL |
LL |
AL |
LL |
||||
Water Quality |
DO |
0 |
0 |
0 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
|
SS |
0 |
0 |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30mins) |
0 |
0 |
0 |
0 |
0 |
0 |
Table A3 Summary of Exceedances for Cultural Heritage in the Reporting Period
Environmental Monitoring |
Parameter |
No. of non-project related exceedances |
Total No. of non-project related exceedances |
No. of exceedances related to the the project |
Total No. of exceedance related to the project |
||||
Alert Level |
Alarm Level |
Action Level |
Alert Level |
Alarm Level |
Action Level |
||||
Cultural Heritage |
Settlement |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Tilting |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Vibration |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Water Quality
A5. No exceedance during impact water quality monitoring was recorded during reporting period.
Noise
A6. No Action Level or Limit Level exceedance was recorded for construction noise monitoring in the reporting period.
Cultural Heritage
A7. No exceedance was recorded for settlement, tilting and vibration monitoring during the reporting period.
A8. The investigation results for the environmental complaint regarding air quality and environmental complaint regarding water quality on 22 January 2025 had been investigated during the reporting period. The summary of the investigation results was presented below:
Environmental Complaint regarding air quality on 22 January 2025
A9. It was recorded that a complaint regarding air quality was received by the EPD on 22 January 2025 and referred to DSD, ET and IEC on 24 January 2025. The complaint was related to the lack of dust suppression measures from the construction site at Lin Fa Tei.
A10. Under the investigation, the precautionary dust suppression measures were implemented on site before and on 22 January 2025 by the contractor. The following measures included:
· Regular watering had been provided for excavated works sites and main haul road;
· Water spraying for vehicle wheeling washing and dust suppression at the exit of the construction sites;
· Paving haul road with concrete to reduce generation of fugitive dust during vehicle travelling; and
· Covering open stockpiles.
A11. To enhance the dust suppression on site, the Contractor had implemented the following measures after 22 January 2025:
· Increasing watering frequency on excavated work sites and main haul roads;
· Ensuring all excavated work sites and main haul roads had adopted proper and regular watering;
· Ensuring water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites; and
· Avoiding open stockpiles placing near air sensitive receivers and ensuring that the stockpiles are covered with tarpaulin when they are not in use.
A12. During the site investigation conducted by the ET at Lin Fa Tei on 22 January 2025 and 28 January 2025, the ET observed that:
· Stockpiles are covered with tarpaulin;
· Water spraying has been adopted on main haul road and exposed area;
· Water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites; and
· No observation of fugitive dust.
A13. Based on the information provided by the Contractor and information collected from the site inspection, it concluded that dust suppression measures have been properly implemented on site to mitigate fugitive dust impact on the nearby residents. No deficiency observation in relation to fugitive dust impact were recorded during the site inspections on 22 and 28 January 2025. After the complaint, the Contractor has enhanced and properly implemented the precautionary and mitigation measures to suppress dust from the work area and within the site boundary. As no further complaint of lacking dust suppression measures was received, the case is considered closed.
Environmental Complaint regarding water quality on 22 January 2025
A14. It was recorded that a complaint regarding water quality was received from 1823 on 22 January 2025 and referred to RE, ET on same day. The complaint was related to the discharge of effluent from the construction site at Lin Fa Tei. Based on the information provided by the Contractor and the information collected from the site inspection, no effluent was discharged at the concerned area (the dewatering pit) and freshwater in the dewatering pit was properly direct to the downstream by water bypass. Therefore, it is concluded that the complaint is invalid.
A15. One environmental complaint regarding air quality and one environmental complaint about waste management were recorded during the reporting period. The relevant investigations are conducting by the related parties. The investigation results will be presented when the investigation has been completed.
A16. No notification of summons or successful prosecutions was received in the reporting period.
A17. No reporting changes in the reporting period.
A18. The major site activities for the next reporting period are summarized below:
§ Site Clearance
§ Breaking Ground
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting
§ Sheet pilling & Backfilling and Compaction; and
§ Removal of Sheet piles, Drain Laying works, Reinstatement
Lin Fa Tei
§ Site Clearance
§ Breaking Ground
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Sung Shan New Village
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Tai Wo
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Diagram 1.1 Organisation Chart
Table 1.1 Parties Involved in Project Organisation
Parties |
Organization / Company |
Project Proponent |
Drainage Services Department |
Supervisor / Engineer’s Representative (ER) |
Atkins China Ltd |
Contractor |
Wing Tat Civil Engineering Co. Limited |
Environmental Team (ET) |
Aurecon Hong Kong Limited |
Independent Environmental Checker (IEC) |
Mott MacDonald Hong Kong Limited |
§ Site Clearance
§ Breaking Ground
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting
§ Sheet pilling & Backfilling and Compaction; and
§ Removal of Sheet piles, Drain Laying works, Reinstatement
Lin Fa Tei
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Sung Shan New Village
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Tai Wo
§ Site Clearance
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Table 1.2 Status of Environmental License, Notifications and Permits
Permit / License No. |
Valid Period |
Status |
|
From |
To |
||
Environmental Permit |
|||
EP-596/2021 |
28/09/2021 |
N/A |
Valid |
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
Ref. Number: 497623 |
29/09/2023 |
N/A |
Valid |
Billing Account for Disposal of Construction Waste |
|||
7048880 |
18/10/2023 |
N/A |
Valid |
Registration of Chemical Waste Producer |
|||
5213-526-W3771-01 |
02/11/2023 |
N/A |
Valid |
Effluent Discharge License under Water Pollution Control Ordinance |
|||
Lin Fa Tei WT10002494-2023 |
24/05/2024 |
31/05/2029 |
Valid |
Tai Wo WT10002495-2023 |
29/07/2024 |
31/07/2029 |
Valid |
Ha Che WT10002496-2023 |
26/04/2024 |
30/04/2029 |
Valid |
Sung Shan New Village WT10002497-2023 |
10/07/2024 |
31/07/2029 |
Valid |
Construction Noise Permit (CNP) |
|||
Lin Fa Tei GW-RN0091-25 |
29/01/2025 |
28/07/2025 |
Valid |
Ha Che GW-RN0092-25 |
01/02/2025 |
31/07/2025 |
Valid |
Sung Shan New Village GW-RN1184-24 |
11/10/2024 |
01/04/2025 |
Valid |
Table 1.3 Summary of Status for Key Environmental Aspects under the Approved Updated EM&A Manual
The baseline water quality monitoring results have been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 4.3. |
|
The regular impact water quality monitoring was commenced at Ha Che on 21 February 2024. Since construction works were commenced at Lin Fa Tei and Tai Wo on 20 March 2024, impact water quality monitoring at Lin Fa Tei (i.e. C6, C7A and C8) and Tai Wo (i.e. C4 and C5) were started 20 March 2024. Impact water quality monitoring at Sung Shan New Village (i.e. C1A, C2 and C3A) was commenced on 17 April 2024 since the construction work at Sung Shan New Village was begun on 16 April 2024. |
|
Up to the end of the reporting period, the baseline noise monitoring results for Ha Che have been reported in the Baseline Monitoring Report and submitted to the EPD under EP Condition 4.3. Baseline noise monitoring results for Tai Wo, Lin Fa Tei, and Sung Shan New Village will be further updated in the Baseline Monitoring Report and submitted to the EPD. The revised Baseline Monitoring Report was submitted to EPD for acceptance on 4 July 2024. |
|
The weekly impact noise monitoring was commenced at Ha Che on 23 February 2024. Since construction works were commenced at Lin Fa Tei and Tai Wo on 20 March 2024, impact noise monitoring at Lin Fa Tei (i.e. LFT_M1, LFT_M3A, LFT_M7 and LFT_M11) and Tai Wo (i.e. TW_M2 and TW_M3) were started 20 March 2024. Impact noise monitoring at Sung Shan New Village (i.e. SSNV_M2, SSNV_M3 and SSNV_M6) was commenced on 19 April 2024 since the construction work at Sung Shan New Village was begun on 16 April 2024. The noise monitoring at LFT_M7 have been suspended since 27 March 2024 due to the objection from property management office for providing access to designated monitoring location. The property management office formally refused our application of access right LFT_M7 on 29 May 2024. An alternative monitoring location LFT_M6 was proposed to replace LFT_M7 and agreed with the ER and the IEC on 29 May 2024 and 4 June 2024 respectively, impact noise monitoring was thus carried out at LFT_M6 from 4 June 2024 onward. |
|
The first draft of HCMP was submitted to the EPD and the Agriculture, Fisheries and Conservation Department (AFCD) on 22 December 2023. Following comments from the EPD and AFCD dated 17 January 2024, the revised HCMP was submitted to EPD and AFCD for further review. Further comment was received from EPD on 27 May 2024, the revised HCMP was submitted to EPD for approval on 13 June 2024. It was accepted by EPD on 9 July 2024. |
|
No suspected contamination was observed or reported by the Contractor in the reporting period. |
|
|
|
The first draft of LVMP was submitted to the EPD, the AFCD and the Planning Department (PlanD) on 22 December 2023. Following comments from the EPD, AFCD and PlanD on 7 February 2024, the LVMP is pending for further revision. The updated LVMP was submitted to EPD for review on 24 July 2024. Comment for LVMP (Rev. 6) was received from EPD on 16 August 2024, the revision of LVMP (Rev. 7) had been submitted to EPD on 21 January 2025. |
|
Weekly Site Audit |
|
The Archaeological Survey at Lin Fa Tei was carried out from 16 to 28 October 2024. The completion brief of archaeological survey was submitted to AMO for review on 30 October 2024. No comment was received from the AMO up to the end of the reporting period. |
|
Site Inspection covering Measures of Air Quality, Noise, Water Quality, Waste, Land Contamination, Ecological Quality, Landscape and Visual Impacts and Cultural Heritage |
Table 2.1 Summary of Impact Water Quality Monitoring Stations
Stream |
Monitoring ID |
Coordinates (HK Grid) |
Remarks |
|
Easting |
Northing |
|||
SSNV |
C1A (1) |
821702 |
831945 |
Alternative Impact Monitoring Point |
C2 |
822459 |
831470 |
Control Monitoring Point |
|
C3A (2) |
822413 |
831284 |
Alternative Control Monitoring Point |
|
TW |
C4 (3) |
825497 |
830664 |
Control Monitoring Point |
C5 (3) |
825486 |
830716 |
Impact Monitoring Point |
|
LFT |
C6 |
827232 |
831713 |
Control Monitoring Point |
C7A (4) |
826865 |
832115 |
Alternative Control Monitoring Point |
|
C8 |
826513 |
832075 |
Impact Monitoring Point |
|
HC |
C9 |
828304 |
835029 |
Control Monitoring Point |
C10 |
827919 |
834271 |
Impact Monitoring Point |
Notes:
(1) At Station C1, access to safe sampling of water is not feasible due to steep banks on both sides of the stream channel. An alternative monitoring location is proposed at Station C1A, which is about 250 m along the same stream channel downstream of Station C1 and is accessible for safe water sampling.
(2) During the first day of baseline monitoring at Station C3, shallow water was observed, and the ET could not sample enough water for monitoring. As agreed by the ER, the Contractor, and the IEC, a new sampling location, Station C3A, was identified at about 130 m upstream and was accessible for water sampling.
(3) Construction works at Tai Wo are only allowed during dry season (i.e. October to March) in accordance with Condition 3.2 of EP No.: EP-596/2021.
(4) For Station C7, the location is not close to the nearest, revised works boundary (about 200 m away). An alternative monitoring location is proposed at Station C7A, which is about 23 m upstream of the nearest, revised works boundary.
Table 2.2 Parameters measured in the Impact Water Quality Monitoring
Parameter |
Frequency |
Duration |
Stream |
Monitoring ID |
Dissolved oxygen (DO), temperature, turbidity, salinity, pH, stream water depth and suspended solids (SS) |
1 day in a week (1) |
Throughout the construction phase |
SSNV |
C1A |
C2 |
||||
C3A |
||||
LFT |
C6 |
|||
C7A |
||||
C8 |
||||
HC |
C9 |
|||
C10 |
||||
3 days in a week |
TW |
C4 |
||
C5 |
(1) Impact monitoring shall be carried out 3 days per week during the construction process. The monitoring frequency can be reduced to once per week, with sampling/ measurement at the designated monitoring locations when no exceedances were recorded during the past three-month period in accordance with Section 2.7, Appendix 4 of the Updated EM&A Manual. The change of the monitoring frequency at SSNV, LFT and HC was approved by EPD on 25 November 2024. Hence, the monitoring frequency at SSNV, LFT and HC was changed to 1 day in a week starting from 2 December 2024.
Dissolved Oxygen and Temperature Measuring Equipment
§ A dissolved oxygen level in the range of 0 – 20 mg/L and 0 – 200% saturation; and
§ The temperature within 0 – 45 °C.
pH
Turbidity Measurement Equipment
Suspended Solids
Water Depth Detector
Monitoring Position Equipment
Water Sampling Equipment
Calibration of In-situ Instruments
Back-up Equipment
Table 2.3 Water Quality Monitoring Equipment
Equipment |
Model |
Quantity |
Serial No. |
Parameter |
Range |
Accuracy |
Water Sampler |
Wildco 2.2L Water Sampler with messenger or plastic bucket (used in shallow water depth) |
1 |
N/A |
N/A |
N/A |
N/A |
Multi-functional Water Quality Meter |
YSI ProDSS (multi-parameters) |
2 |
22D100436, and 22C106561 |
Dissolved Oxygen (DO) |
0 to 500% |
· 0 to 200%: ±1% of reading · 200 to 500%: ±8% of reading |
0 to 50 mg/L |
· 0 to 20 mg/L: ±0.1 mg/L or 1% of reading, whichever is greater · 20 to 50 mg/L: ±8% of reading |
|||||
Temperature |
-5 to 50 °C |
±0.2 °C |
||||
pH |
0 to 14 pH units |
±0.2 pH units |
||||
Turbidity |
0 to 4000 NTU |
· 0 to 999 NTU: 0.3 NTU or ±2% of reading, whichever is greater · 1000 to 4000 NTU: ±5% of reading |
||||
Salinity |
0 to 70 ppt |
· ±1.0% of reading or ±0.1 ppt, whichever is greater |
||||
Water Depth Ruler |
鼎峯0708 |
1 |
N/A |
Water depth |
0 – 7 m (Used for water depth less than 1 m) |
±0.01 m |
Positioning Equipment |
Garmin (GPSmap 78s) |
1 |
1WL223754 |
Positioning |
N/A |
GPS: ±1m |
Laboratory Analytical Methods
Table 2.4 Method for Laboratory Analysis for Water Samples
Parameters |
Analytical Method |
Detection Limit |
Suspended Solid (SS) |
APHA 17ed 2540-D (1) |
1 mg/L or better |
Note:
(1) APHA American Public Health Association Standard Methods for the Examination of Water and Wastewater.
Decontamination Procedures
Sampling Management and Supervision
Quality Control Measures for Sample Testing
§ One method blank; and
§ One set of QC sample
Table 2.5 Action and Limit Levels for Water Quality
Action Level |
Limit Level |
|
DO in mg/L |
< 5%-ile of baseline data |
< 4 mg/L or < 1%-ile of baseline data |
SS in mg/L |
> 95%-ile of baseline data or >120% of upstream control station of the same day, whichever is higher |
> 99%-ile of baseline data or 130% of upstream control station of the same day, whichever is higher |
Turbidity in NTU |
> 95%-ile of baseline data or >120% of upstream control station of the same day, whichever is higher |
> 99%-ile of baseline data or > 130% of upstream control station of the same day, whichever is higher |
(1) For DO, non-compliance of the water quality limit occurs when monitoring result is lower than the limit.
(2) For SS and turbidity, non-compliance of the water quality limit occurs when monitoring result is higher than the limits
(3) All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered necessary.
Table 2.6 Action and Limit Levels of Water Quality
Monitoring ID |
Parameters |
Action |
Limit |
|
SSNV |
C1A |
DO in mg/L |
<6.72 |
<4 (1) |
SS in mg/L |
>7.3 or >120% of upstream control station of the same day, whichever is higher |
>8.5 or > 130% of upstream control station of the same day, whichever is higher |
||
Turbidity in NTU |
>10.37 or >120% of upstream control station of the same day, whichever is higher |
>10.81 or > 130% of upstream control station of the same day, whichever is higher |
||
TW |
C5 |
DO in mg/L |
<8.36 |
<4 (2) |
SS in mg/L |
>9.9 or > 120% of upstream control station of the same day, whichever is higher |
>10.0 or > 130% of upstream control station of the same day, whichever is higher |
||
Turbidity in NTU |
>13.64 or > 120% of upstream control station of the same day, whichever is higher |
>13.87 or > 130% of upstream control station of the same day, whichever is higher |
||
LFT |
C8 |
DO in mg/L |
<5.38 |
<4 (3) |
SS in mg/L |
>6.3 or > 120% of upstream control station of the same day, whichever is higher |
>7.0 or > 130% of upstream control station of the same day, whichever is higher |
||
Turbidity in NTU |
>12.46 or > 120% of upstream control station of the same day, whichever is higher |
>12.94 or > 130% of upstream control station of the same day, whichever is higher |
||
HC |
C10 |
DO in mg/L |
<2.55 |
<2.43 (4) |
SS in mg/L |
>8.7 or > 120% of upstream control station of the same day, whichever is higher |
>8.8 or > 130% of upstream control station of the same day, whichever is higher |
||
Turbidity in NTU |
>20.06 or > 120% of upstream control station of the same day, whichever is higher |
>21.07 or > 130% of upstream control station of the same day, whichever is higher |
(1) The 1%-ile of baseline DO data at C1A is 6.61 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(2) The 1%-ile of baseline DO data at C5 is 8.09 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(3) The 1%-ile of baseline DO data at C8 is 5.36 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(4) The 1%-ile of baseline DO data at C10 is 2.43 mg/L, which is lower than 4 mg/L. Taking account of the baseline water quality condition and to minimise any false alarm of water quality deterioration during construction phase, DO concentration of 2.43 mg/L is adopted as the limit level.
Table 2.7 Summary of Exceedance Records of Water Quality Monitoring in the Reporting Period
Parameter |
No. of non-project related exceedances(1) |
Total No. of non-project related exceedances |
No. of exceedance related to the Project |
Total No. of exceedance related to the Project |
||
AL |
LL |
AL |
LL |
|||
Dissolved Oxygen |
0 |
0 |
0 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
Suspended Solids |
0 |
0 |
0 |
0 |
0 |
0 |
Table 3.1 Noise Monitoring Stations during Construction Phase
ID No. (1) |
Location |
Nature of Uses |
Type of Measurement |
SSNV_M2 |
Village house next to a nullah in Tong Tai Po Tsuen (near DD118 1720 S.A) |
Residential |
Façade |
SSNV_M3 |
Village house near a soybean sauce factory in Sung Shan New Village (near DD118 1712) |
Residential |
Façade |
SSNV_M6 |
#43, Sung Shan New Village |
Residential |
Free-field |
TW_M2 (4) |
#200, Cheung Po |
Residential |
Free-field |
TW_M3 (4) |
Kai Yip Garden, #3H, Tai Wo |
Residential |
Free-field |
LFT_M1 |
#2G, Lin Fa Tei |
Residential |
Façade |
LFT_M3A (2) |
Near #125B, Lin Fa Tei |
Residential |
Free-field |
LFT_M5 |
#156B, Lin Fa Tei |
Residential |
Façade |
LFT_M6 (3) |
#47, Shui Tsan Ti |
Residential |
Façade |
LFT_M11 (2) |
#210, Ngau Keng Tsuen |
Residential |
Façade |
HC_M3A (2) |
Next to DD111 326 S.B RP near Fan Kam Road |
- |
Free-field |
HC_M4 |
#1C, Chuk Hang |
Residential |
Façade |
HC_M6 |
The Arbutus House 12, #52, Shui Kan Shek |
Residential |
Façade |
Notes:
(1) SSNV – Sung Shan New Village; TW – Tai Wo; LFT – Lin Fa Tei; HC – Ha Che.
(2) LFT_M3A, LFT_M11, HC_M3A and are alternative noise monitoring stations proposed to replace LFT_M3, LFT_M13 and HC_M3, respectively.
(3) Due to the objection from property management office for providing access to designated monitoring location, the noise monitoring at LFT_M7 have been suspended since 27 March 2024. An alternative monitoring location LFT_M6 was proposed to replace LFT_M7 and agreed with the ER and the IEC.
(4) Construction works at Tai Wo are only allowed during dry season (i.e. October to March) in accordance with Condition 3.2 of EP No.: EP-596/2021.
Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration
Monitoring Station |
Parameter |
Frequency and Duration |
SSNV_M2, SSNV_M3, SSNV_M6, HC_M3A, HC_M4, HC_M6, TW_M2, TW_M3, LFT_M1, LFT_M3A, LFT_M5, LFT_M6 and LFT_M11 |
Leq(30mins) (as a logarithmic average of 6 consecutive Leq(5mins)) |
Once every week throughout the construction phase |
§ For façade measurement, the monitoring station was set at a point 1 m from the exterior of the sensitive receivers building façade and set at a position 1.2 m above the ground. For free-field measurement, the monitoring station was set at a position 1.2 m above the ground.
§ The battery condition was checked to ensure good functioning of the meter.
§ Parameters such as frequency weighting, the time weighting and the interval were set as follows:
- Frequency weighting: A
- Time weighting: Fast
- Interval: 30 minutes (Leq(30mins)) would be determined for daytime noise by calculating the logarithmic average of six Leq(5mins) data
§ Prior to and after each noise measurement, the meter was calibrated using an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement will be required after re-calibration or repair of the equipment.
§ At the end of the monitoring period, the values of Leq, L90 and L10 were recorded. In addition, noise sources were recorded on a standard record sheet.
Table 3.3 Construction Noise Monitoring Equipment
Equipment |
Model |
No. of Equipment |
Serial No. |
Sound Level Meter |
NTi Audio XL2 |
1 |
A2A-09696-E0 |
Acoustic Calibrator |
Rion NC-75 |
1 |
34724244 |
§ The microphone head of the sound level meter and calibrator were regularly cleaned with a soft cloth; and
§ The sound level meter and acoustic calibrator were calibrated annually by a HOKLAS accredited laboratory or the manufacturer.
Table 3.4 Action and Limit Levels for Construction Noise Monitoring
Time Period |
Action |
Limit Level |
07:00 – 19:00 on normal weekdays |
When one or more documented complaints are received |
75 dB(A)(1) |
07:00 – 23:00 on holidays; and 19:00 – 23:00 on all other days |
45 dB(A)(2) |
|
23:00 – 07:00 of the next day |
30 dB(A)(2) |
(1) Between 07:00 and 19:00, construction noise limit for school during normal term time is 70 dB(A) and 65 dB(A) during examination period.
(2) The ASR of identified noise sensitive receivers is “A”, which is a rural area that is not affected by the in Influencing Factors (Ifs). The limit levels are stipulated in the Technical Memorandum on Noise from Construction Work in Designated Areas.
Table 3.5 Summary of Construction Noise Monitoring Results
Monitoring Station |
Noise Level, dB(A) |
Limit Level |
|
Leq(30mins) |
|||
Minimum |
Maximum |
||
SSNV_M2 |
50.1 |
53.0 |
75 dB(A) |
SSNV_M3 |
59.7 |
62.3 |
75 dB(A) |
SSNV_M6(1) |
63.8 |
65.3 |
75 dB(A) |
TW_M2(1) |
54.3 |
55.2 |
75 dB(A) |
TW_M3(1) |
55.0 |
55.3 |
75 dB(A) |
HC_M3A(1) |
66.8 |
70.3 |
75 dB(A) |
HC_M4 |
62.3 |
64.0 |
75 dB(A) |
HC_M6 |
61.6 |
65.1 |
75 dB(A) |
LFT_M1 |
61.6 |
62.6 |
75 dB(A) |
LFT_M3A(1) |
60.6 |
61.7 |
75 dB(A) |
LFT_M5 |
58.3 |
61.1 |
75 dB(A) |
LFT_M6 |
59.6 |
62.9 |
75 dB(A) |
LFT_M11 |
56.4 |
58.3 |
75 dB(A) |
Note:
(1) For Free Field measurement, +3 dB(A) was added to the measured results.
Table 3.6 Influencing Factors at Noise Monitoring Stations
Monitoring Stations |
Influencing Factors |
SSNV_M2 |
Nil |
SSNV_M3 |
Nil |
SSNV_M6 |
Nil |
TW_M2 |
Nil |
TW_M3 |
Nil |
HC_M3A |
Road Traffic Noise |
HC_M4 |
Road Traffic Noise |
HC_M6 |
Road Traffic Noise |
LFT_M1 |
Nil |
LFT_M3A |
Nil |
LFT_M5 |
Road Traffic Noise |
LFT_M6 |
Nil |
LFT_M11 |
Road Traffic Noise |
Plate 4.1 Site condition of receptor sites at Ha Che and Lin Fa Tei during the reporting month
Upper receptor site for Cryptopotamon anacoluthon at Ha Che |
Lower receptor site for Somanniathelphusa zanklon at Ha Che |
Receptor site for Cryptopotamon anacoluthon and Somanniathelphusa zanklon at Lin Fa Tei
Table 4.1 Summary of Freshwater Crab Species Captured during the Post-Translocation Monitoring
Species |
ID No./Code |
Sex |
Carapace Size (mm) |
Receptor Site |
Time of Capture |
Remarks |
C. anacoluthon |
New Individual |
M |
13.3 |
Ha Che Upper |
19:19 |
/ |
Table 8.1 Mitigation Measures for Impacted Graded Historic Buildings
Graded Historic Buildings |
Mitigation Measures |
Lee Tat Bridge, Shui Tsan Tin (Grade 3) |
§ A condition survey should be carried out in advance of works and after completion of works by qualified building surveyor or structural engineer. The Condition Survey Report should contain descriptions of the structure, identification of fragile elements, an appraisal of the condition and working methods for any proposed monitoring and precautionary measures that are or were recommended with aid of photo records. The condition survey report must be submitted to the AMO for comment before construction activities commence and after the works have been completed. The contractor should implement the approved monitoring and precautionary measures. § Vibration, settlement and tilting monitoring should be undertaken during the construction works to ensure that safe levels of vibration are not exceeded. An Alert, Alarm and Action (AAA) vibration limit set at 5 / 6 / 7.5 mm/s for Grade 3 historic buildings, settlement limit set at 6/ 8/ 10mm, and tilting limit set at 1/2000; 1/1500; 1/1000 should be adopted. Monitoring proposal, including checkpoint locations, installation details, response actions for each of the AAA levels and frequency of monitoring should be submitted for AMO's consideration. Installation of monitoring checkpoints shall be carried out in great care and adequate protection shall be provided so as to avoid unnecessary disturbance/ damage to the historic fabrics. Photo records of monitoring checkpoints shall be submitted upon installation for AMO's records. Monitoring records should be submitted to AMO on regular basis and alert AMO should the monitoring reach AAA levels. |
Lan Fong Study Hall, Chuk Hang (Grade 3) |
|
St John’s Chapel, Cheung Po (Grade 2) |
Table 9.1 Site Inspection Record
Date |
Inspected Site Portion |
Time |
5 February 2025 |
Ha Che |
14:30 – 15:00 |
12 February 2025 |
Lin Fa Tei |
14:30 – 15:00 |
19 February 2025 |
Sung Shan New Village |
14:00 – 15:00 |
26 February 2025 |
Tai Wo |
11:00 – 11:30 |
Date |
Environmental Observations |
Follow-up Status |
5 Feb 2025 |
Observation(s) and Recommendation(s)
Ha Che: 1. The Contractor was reminded to place the updated CNP on site. |
Ha Che: 1. The updated CNP has been displayed on site by the contractor. |
12 Feb 2025 |
Observation(s) and Recommendation(s)
Lin Fa Tei: 1. The Contractor was reminded to direct waterflow to the wastewater treatment system before discharge especially during rainy day. |
Lin Fa Tei: 1. The water flow was redirected to the wastewater treatment system before discharge by the contractor. |
19 Feb 2025 |
Observation(s) and Recommendation(s)
Nil |
Nil |
26 Feb 2025 |
Observation(s) and Recommendation(s)
Nil |
Nil |
Environmental Complaint regarding air quality on 22 January 2025
· Regular watering had been provided for excavated works sites and main haul road;
· Water spraying for vehicle wheeling washing and dust suppression at the exit of the construction sites;
· Paving haul road with concrete to reduce generation of fugitive dust during vehicle travelling; and
· Covering open stockpiles.
· Increasing watering frequency on excavated work sites and main haul roads;
· Ensuring all excavated work sites and main haul roads had adopted proper and regular watering;
· Ensuring water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites; and
· Avoiding open stockpiles placing near air sensitive receivers and ensuring that the stockpiles are covered with tarpaulin when they are not in use.
· Stockpiles are covered with tarpaulin;
· Water spraying has been adopted on main haul road and exposed area;
· Water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites; and
· No observation of fugitive dust.
Environmental Complaint regarding water quality on 22 January 2025
Ha Che
§ Site Clearance
§ Breaking Ground
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting
§ Sheet pilling & Backfilling and Compaction; and
§ Removal of Sheet piles, Drain Laying works, Reinstatement
Lin Fa Tei
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Sung Shan New Village
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Tai Wo
§ Site Clearance
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and
§ Sheet pilling & Backfilling and Compaction
Noise
§ Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and
§ Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
§ Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;
§ Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;
§ Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;
§ Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and
§ Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.
Waste Management
§ Provision of sufficient waste disposal points and regular collection of waste;
§ Regular cleaning and maintenance programme for drainage system; and
§ Chemical containers shall be stored with drip tray underneath.
Ecology
§ Minimize loss of habitats and associated wildlife; and
§ Using directional lighting to prevent excessive light spill into adjacent natural habitat and disturbance to nocturnal fauna.
Landscape and Visual
§ Construction activities shall be carefully designed to minimize impact on existing retained trees; and
§ Adequate tree protection measures shall be provided for the trees to be retained on site.
· Regular watering had been provided for excavated works sites and main haul road;
· Water spraying for vehicle wheeling washing and dust suppression at the exit of the construction sites;
· Paving haul road with concrete to reduce generation of fugitive dust during vehicle travelling; and
· Covering open stockpiles.
· Increasing watering frequency on excavated work sites and main haul roads;
· Ensuring all excavated work sites and main haul roads had adopted proper and regular watering;
· Ensuring water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites; and
· Avoiding open stockpiles placing near air sensitive receivers and ensuring that the stockpiles are covered with tarpaulin when they are not in use.
· Stockpiles are covered with tarpaulin;
· Water spraying has been adopted on main haul road and exposed area;
· Water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites; and
· No observation of fugitive dust.